Adding and updating tasks

Tasks break projects down into individual processes and can help your firm streamline its workflow by providing up-to-date information and notifications when subsequent tasks are ready to be worked on.

Adding a task to a project

To add a task to a client’s project, follow these steps.
  1. Open the
    Project
    dialog.
    There are several ways to access the
    Project
    dialog:
    • In the
      Clients
      setup screen (Setup > Clients), select the client for which you want to add task information and select the
      Edit
      button. On the Projects tab, select the
      Add
      or
      Edit
      button to open the
      Projects
      dialog.
    • In the
      Manage Projects
      screen (Actions > Manage Projects), right-click the project list and choose either
      Add Project
      or
      Edit Selected Projects
      from the context menu.
    • You can also right-click any
      Project
      field (for example, in Time & Expense Entry) and choose
      Add Project
      or
      Edit Project
      from the context menu.
  2. In the
    Project
    dialog, go to the Tasks tab.
  3. Select the
    Add
    button to open the
    Task
    dialog.
  4. Identification:
    • Order:
      The default order number is 1 for the first task that you add to a project. For each additional task, the application assigns the next available number. However, you can enter a duplicate order number, if necessary.
      note
      For tasks that are concurrent, you may want to use duplicate order numbers. When the preceding task is completed, notifications will be sent that both concurrent tasks are ready if you have set up notifications at the Firm level. Both of those tasks must be completed before a notification is sent that the next task is ready.
    • Activity:
      Select the activity for the current task.
    • Description:
      If you want the task description to be something other than the default description inherited from the Activity, enter a new description.
  5. Task information: Make a selection in the
    Tracking
    field. The default for new tasks is Not Started. Select a tracking description from the drop-down list. If you have security permission, you can right-click to add or edit a tracking description in the drop-down list.
  6. Budget information: Mark the
    Calculate amount automatically
    checkbox to have the budgeted amount calculate automatically based on the staff rate of the assigned staff member. Leave the checkbox unmarked if you want to enter the task budget information in the
    Hours Budgeted
    and/or
    Amount Budgeted
    fields manually or select the Down arrow button and use the drop-down calculator to enter the numbers. You can also make manual adjustments to the number shown in the
    Est. Remaining
    field.
  7. Target dates:
    • Start:
      To specify the project’s target start date, complete the
      month(s)
      and/or
      day(s)
      fields, and then select
      Before due date
      or
      After received date
      from the drop-down list.
    • Complete:
      To specify the target completion date, complete the
      month(s)
      and/or
      day(s)
      fields, and then select
      Before due date
      or
      After received date
      from the drop-down list.
  8. Assigned: Select the More button to select a staff to assign to the project.
    If you are licensed for the Staff Management module, you can also:
    • manually assign staff to the task based on their qualifications. Select a filter from the list, or select the More button next to the
      Staff qualifications
      field and create a filter to specify which qualifications the assigned staff must possess to work on the task.
    • automatically assign staff to the task based on a work queue. When you select the
      Work queue
      option, the task will be placed in a queue that appears in the Work Queue portlet of the Staff Dashboard only for those staff who meet the qualifications.
    • go to the Scheduling tab to view the schedules of all qualified staff members and assign the task to a staff member or to the work queue by marking the appropriate checkbox.
  9. Solution:
    • Select solution:
      Select the solution you will use to complete the task from the drop-down list. This field defaults to the solution for the project.
      When you select a solution (Microsoft Word or Excel, or other application) for a project or task, DT Practice will do the following when you launch the solution from the project or task:
      • If the client exists in the solution that you have selected, the client will be opened automatically.
      • If you have entered a file path for Word or Excel, the document in the file path will open automatically.
      • DT Practice will automatically start a timer, if you have the
        Start Timer for Projects
        checkbox marked in Setup > User Preferences > Time & Expense Entry. When you close the client, document, or application, the timer is stopped. You then need to post the recorded time to Time & Expense Entry.
      If the solution you want to use is not available in the drop-down list, enter the path in the
      Solution path
      field and select the More button to navigate to the solution.
  10. Notes: Enter an optional comment in the text box.
  11. Go to the Scheduling tab if you want to view the schedules of all qualified staff members. You can assign the task by marking the checkbox for a staff member or the work queue.
  12. The Links tab enables you to add links to any items that you want to associate with the task. You can link to files, websites, or documents outside of DT Practice, including documents stored in DT FileCabinet. You can also link to interaction items within DT Practice.
    The links you add to a task apply only to the task to which you add them. You can also add links to task templates, which apply to all new tasks generated from that template.
  13. The Custom Fields tab provides fields in which you can enter additional information for the task. Custom fields can be checkboxes, dates, lists, numeric fields, staff lists, or text-entry fields. Custom fields for dates have a drop-down calendar. Numeric custom fields have a drop-down calculator. DT Practice allows you to create your own custom fields and field names for offices, staff, activities, clients, engagements, projects, tasks, and time & expense entry. Using custom fields enables you to track additional information in the application. You can create checkboxes, date fields, numeric fields, text fields (up to 4000 characters long), lists, and staff lists. To create custom fields, choose Setup > Custom Fields and then Offices, Staff, Activities, Clients, Engagements, Projects, Tasks, or Time & Expense Entry, depending on where you want the custom fields to appear within DT Practice.
  14. Select
    OK
    to save the task.

Updating task information

  1. Select the task that you want to update.
    There are several ways to select a task:
    • In the Clients setup screen (Setup > Clients), select the client for which you want to update task information and select the
      Edit
      button. Go to the Projects tab, expand the project to which the task belongs, and select the task. Then select the
      Edit
      button (or right-click the task and choose Edit Task) to open the
      Task
      dialog.
    • In the
      Project
      dialog, go to the Tasks tab, and select the task that you want to update.
    • In the
      Manage Projects
      screen, select the project in the entry grid, then right-click the task you want to update in the lower part of the grid and choose
      Edit Selected Tasks
      from the context menu.
    • In the
      Manage Projects
      screen, go to the Project Tasks tab. Right-click the task that you want to update and choose
      Edit Selected Tasks
      from the context menu.
    • In the
      Time & Expense Entry
      screen, select a project from the drop-down list in the
      Project
      field. Select the Task Selection button to open the
      Task Selection
      dialog and select the task that you want to update.
  2. Select the
    Edit
    button or right-click and choose
    Edit Task
    from the context menu.
  3. Update the task information as needed.
    note
    • When you change the
      Tracking description
      field to Completed, the application automatically enters the date in the
      Complete
      field under Actual dates. You can edit these dates, if necessary.
    • When you enter an Actual Start or Complete date, the application changes the
      Tracking description
      field to Started or Completed, respectively.
    • To update multiple tasks simultaneously, hold down the SHIFT or CTRL key as you make your selections, then right-click and choose Edit Selected Tasks from the context menu. In the Edit Selected Tasks dialog, choose a field to update for the selected tasks and a new value to enter in that field. You can update up to six fields at once in this dialog.
  4. Select
    OK
    to save your changes.