Project percent complete example

In the
Project
dialog, the
% Complete
field shows a calculated percentage of budgeted hours for all completed tasks relative to the total budgeted hours for the project.
Example:
Item
Task Budgeted Hours
Tracking
Task 1
5.0
Completed
Task 2
2.0
Completed
Task 3
3.0
Not Started
Project Total Budgeted Hours
10.0
N/A
% Complete:
(5.0 + 2.0) / 10 = 0.70, or 70%