The Project Tracking report enables you to track the status of projects in Digita Practice Advanced. The report lists staff members involved with the project; important dates such as start, received, and complete dates; and the number of times the project has been extended.
This report is available only if you are licensed for the Project Management module.
To view and print the Project Tracking report, choose File > Print Reports. In the Print Reports screen, click Project Tracking in the available reports pane and then click the Select button.
Information on the report includes the following:
ID, Project Description
: The number and description assigned to the project at setup
Client Name
: The client assigned to the project
Responsible
: The staff member assigned to the project at setup
Priority
: The priority (Low, Normal, or High) assigned to the project at setup
Target Start / Target Complete
: The target dates assigned to the project at setup
Received
: The date that the project was received
Actual Start / Actual Complete
: The actual start and complete dates entered for the project
Current Due Date
: The due date entered for the project at setup
Tracking
: Indicates the status of the project
Ext
: The number of times the project has been extended
When you enable security privileges for a report on the Security Groups setup screen, Digita Practice Advanced may also enable privileges to view the data available on the report. Conversely, removing privileges for viewing data may also remove privileges for related reports. Consult the
Privileges changed
pane on the Security Groups setup screen to see all privilege changes that are triggered by enabling access to a report.
For this report, if no privileges are already enabled for the following security option(s), full privileges will be enabled.
Data > Schedule Item Data > Project Data > View
If your firm has multiple offices, you may want to rescind privileges to information for other offices.