Adding template information
Some items in the drop-down lists in this screen come from entries you have made via the Setup menu (for example, Setup > Tracking Descriptions). If you have security privileges to do so, you can also right-click in these drop-down lists to add, edit, or delete items from the list.
In the Project Templates screen, click the Main tab and complete the fields as necessary.
Identification:
In the
ID
field, enter a unique alphanumeric ID, up to 11 characters.
This is a required field. The ID will be saved in upper case letters regardless of how it is entered.
In the
Description
field, enter a brief description of the project that will be easily recognizable to your staff.
In the
Invoice description
field, enter a description of the project as you want it to appear on client invoices.
Project information:
Engagement:
Select the engagement to be used for the project. This is a required field. If you have security privileges, you can right-click to add or edit an engagement in the drop-down list.
Priority:
Select Low, Medium, or High as the priority for the project.
Tracking:
Select a tracking description for the project. If you have security privileges, you can right-click to add or edit tracking descriptions in the drop-down list.
Groupings: Groupings let you categorize project templates for filtering the list of projects and for creating reports. You can group projects by the staff responsible and by department. Click the down arrow Down arrow

button and select a staff role (for example, Client’s Manager) to have the application complete this information using the client’s assignments.
Entities: Click the More

button to select the client entities to assign to the project. When you assign an entity to the project, the application can automatically create this project for new clients that are assigned this entity. The
Associated Entities
field shows all of the entities that have been assigned to the project template.
Budget information: Mark the
Base on tasks
checkbox if you want to base budget information on the information set up on the project’s tasks. Mark the
Calculate amount automatically
checkbox to calculate budget information based on staff rates. Leave the checkboxes unmarked if you would like to enter the budget information yourself in the
Hours
and/or
Amount
fields.
Assigned: Click the More

button next to the
Staff
field to select a staff member to assign to the project, or click the Down arrow

button to assign a staff member dynamically based on their role (for example, Client’s Partner, or Engagement’s Biller). If you are licensed for the Staff Management module, you can also:
manually assign staff to the project based on their qualifications. Click the More

button next to the
Staff qualifications
field and create a filter to specify which qualifications the assigned staff member must possess to work on the project.
automatically assign staff to the project based on a work queue. When you mark the
Work queue
option, the project will be placed in a queue that appears in the Work Queue portlet of the Staff Dashboard only for those staff who meet the qualifications.
Generation: Click the Recurrence button to open the Recurrence dialog, where you can specify the project frequency, dates, and generation options for future projects.
Solution:
Select solution:
Select a solution you will use to work on the project from the drop-down list.
Solution path
or
File path:
If you select Other for the solution, click the More

button to navigate to the solution’s shortcut or application file.
Extensions: If you want to be able to extend a project’s due date, enter the number of months and/or days from the original due date for each extension. The maximum number of extensions allowed is four.
If you do not set up extensions on the project template, extensions will not be available when you use it to create a project. Also, extensions that you add to a project template are not added to projects that have already been created. However, you can still extend an existing project by right-clicking and choosing Add Entry from the context menu in the Project dialog.
This tab shows selected task information associated with the current project template, including the activity, staff, target completion month and day, and tracking description.
To add a task to the project template, click the Add button and complete the information in the Task Template setup dialog. You can also double-click a row in the grid to open the Task Template dialog. Click on any column heading to sort the tasks grid by items in that column.
The Links tab enables you to add links to any items that you want to associate with the project template. You can link to files, websites, or documents outside of Digita Practice Advanced, including documents stored in Digita FileCabinet. You can also link to interaction items within Digita Practice Advanced.
The links you add to a project template will be added by default to all new projects generated from that template.
To add a link to the project template, right-click within the Links tab and choose the command from the context menu that pertains to the type of link you want to add. Navigate to that item and click OK.
The Custom Fields tab provides fields in which you can enter additional information for the project template. Custom fields can be checkboxes, dates, lists, numeric fields, staff lists, or text-entry fields. Custom fields for dates have a drop-down calendar. Numeric custom fields have a drop-down calculator.