Project percent complete example
In the Project dialog, the
% Complete
field shows a calculated percentage of budgeted hours for all completed tasks relative to the total budgeted hours for the project.Example:
Item | Task Budgeted Hours | Tracking |
|---|---|---|
Task 1 | 5.0 | Completed |
Task 2 | 2.0 | Completed |
Task 3 | 3.0 | Not Started |
Project Total Budgeted Hours | 10.0 | N/A |
% Complete:
(5.0 + 2.0) / 10 = 0.70, or 70%