Override due date records

You can override due date records individually, in bulk, or via import.

Override individual due dates

  1. Select the
    Edit Properties
    screen, then enter a new
    Due Date
  2. Select Save.

Override due dates in bulk

  1. Select the checkboxes for the rows you want to override on the
    Due Dates
    tab.
  2. Select
    Override
    .
  3. Enter the new date for all selected records.
  4. Select
    Apply
    .
    Result:
    • The
      Due Date
      changes to the new date you entered.
    • The
      Due Date in Use
      changes to Overridden status.
    • The
      Extensions Remaining
      doesn't change.

Override due dates via import

  1. Filter the due dates you want to update on the
    Due Dates
    tab.
  2. Select
    Import & Update
    ,
    Export for Update
    to obtain an Excel file with all fields available for update.
  3. Change the
    Due Date
    to the new date. You don't have to change the
    Due Date in Use
    . The calendar will do that after import.
  4. Save the import file.
  5. Import the updated file by selecting
    Import & Update, Import
    . You can find the results of the import on the
    Process Queue
    tab.