43147 e-file error
* 43147: Schedule NJK-1 Part I, Date Partner's Interest in Partnership began must be present.
This happens when you haven’t entered the Date interest began in New Jersey for the partners.
Solution 1
- InOrganizer, selectPartner Information, then thePartner by Partner Datafolder.
- SelectColumnar Partner Entry, then theState Informationtab.
- Go to theState Information for Partnerssection, select theNew Jerseyhyperlink.
- Go to thePartners' State Information - Maryland to New Mexicosection.
- In theDate Partner's Int Began in NJcolumn, enter the date for all partners.
- Do a full recompute and recreate the e-file.
Solution 2
- InOrganizer, selectPartner Information, then thePartner by Partner Datafolder.
- Select thePartner Namefolder.
- SelectPartner Information, then go to theState Partner Informationtab.
- Go to theNew Jerseysection.
- Enter the date in LineDate interest began in New Jersey.
- Do a full recompute and recreate the e-file.