Change the status of a task in a completed project
To change the status of a task in a completed project, you must first set the project status to something other than Completed, then update the task.
When you mark a project as Completed, Practice CS automatically marks all of its tasks as Completed. To change the status of an individual task, you must first change the project status away from Completed.
- Open the project by double-clicking it or selectingEdit.
- Select theMaintab and change the Tracking Description to any status other than Completed.
- SelectOK.
- Select theTaskstab and open the task you want to update by double-clicking it or selectingEdit.
- Change the Tracking Description to the required status.
- SelectOK.