Populate UltraTax CS completion events in a Practice CS project template
The Practice CS Project Management module lets you specify an event in UltraTax CS that, when logged, automatically updates the tracking description on a project or task to
Completed
.To ensure this process works correctly, make sure the completion event you enter in the project or task matches the event description in UltraTax CS exactly. You can ensure the events match by populating the list of events from UltraTax CS in Practice CS using the following steps.
- In Practice CS, go to .
- Go to thePreferencestab and verify that you've marked theIntegrate this Firm with other solutionscheckbox. If not, mark it and selectEnterto save the change.
- Open UltraTax CS.
- SelectFile, thenOpen Clientand open a client.
- Log any event for the client by selectingUtilities, thenClient Status, or using theF5key.
- SelectFile, thenClose Client.
- In Practice CS, go to .
- Select a project template, thenEdit.
- In theSolutionsection, selectUltraTax CSfrom theSelect solutiondropdown.
- Use theCompletion Eventdropdown to verify that Practice CS now displays the UltraTax CS status events in the list of available items.
- To set the completion event for this project or task, select the event from the list.
- If needed, set an extension event. The UltraTax events will also appear in this list.