Change the order of tasks in a project
You can change the order of the tasks by changing the order number.
note
- Order Numbers don't need to be contiguous.
- The tasks don't need to be listed by order number. The application will follow the order specified by the order numbers regardless of where they appear on the list of tasks.
- Multiple tasks can have the same order number. Tasks are given the same order number when they can be worked on simultaneously and aren't dependent on one another.
- Tasks don't need to be completed in the order specified by the order number. The order number is used only to determine which task is to be marked as ready to be worked on. If tasks are completed out of order, the uncompleted task with the lowest order number will be marked as ready.
Follow these steps to change the order of tasks in a project.
- SelectActions, thenManage Projects.
- Double-click the project.
- Select theTaskstab.
- Select a task, thenEdit.
- Change the number in theOrderfield.
- SelectOK.
- Repeat steps 4 through 6 for each task to change the order number.
- SelectOKto save the project.
Follow these steps to change the order of a large number of tasks for a project.
- Make the changes to the tasks you want on the specified projects to the template on which they were based. This includes adding tasks, deleting tasks, or changing the order numbers on tasks.
- On theMaintab of the project, select

- Clear theTask informationcheckbox forProject Generation Options.
- SelectOKto save the changes to the Recurrence settings.
- SelectEnterto save the changes to the template.
- SelectActions, thenManage Projects.
- Filter, sort, and/or group the projects to find the ones with the tasks to reorder.
- Select all projects, then right-click and selectDelete Selected Projects.
- Filter, sort, and/or group the previous occurrence of the projects you just deleted.noteIf these projects are completed, you must clear theOpen Projects onlycheckbox.
- Select all the projects, then right-click and selectEdit Selected Projects.
- SelectChange Project information, thenNext.
- SelectRecurrence, then

- UnderRecurrence, selectUse Project Template.
- SelectOK.
- SelectFinish.
- With the projects still selected, right-click and selectGenerate Next Project.The occurrence of the projects you deleted in step 8 will be regenerated with the newly ordered tasks.