Extend a project due date

Use the
Extension
dialog to add, change, or delete a project due date extension.
When a project template is set up with extensions before a project is created for a client, you can extend the project by selecting an extension from the dropdown list in the
Due dates
section of the
Project
window. If the project template didn’t include extensions before the project was created, you can add them later by using the
Extension
window.
To open the
Extension
window, right-click the dropdown list under
Due dates
in the
Project
window, and then select
Add Entry
or
Edit Entry
.
note
Extensions added to a project template are not added automatically to projects that have already been created. To add an extension to an existing project, use
Add Entry
from the context menu.
  1. Open the
    Project
    window.
    You can access the
    Project
    window in any of the following ways:
    • In the
      Clients
      setup screen, choose
      Setup
      Clients
      , select the client, select
      Edit
      , open the
      Projects
      tab, select the project, and then select
      Edit
      .
    • In the
      Manage Projects
      screen, choose
      Actions
      Manage Projects
      , right-click the project list, and then choose
      Add Project
      or
      Edit Selected Projects
      .
    • Right-click any
      Project
      field, such as in
      Time & Expense Entry
      , and then choose
      Add Project
      or
      Edit Project
      .
  2. Right-click the dropdown list under
    Due dates
    .
  3. Do one of the following:
    1. To add an extension, select
      Add Entry
      .
    2. To change an extension, select
      Edit Entry
      .
    3. To delete an extension, select
      Delete Entry
      .
  4. If you are adding or editing an extension, complete the fields in the
    Extension
    window.
    1. Enter or update the value in the
      Extension number
      field.
    2. Enter the extended date in the
      Due date
      field, or select it from the calendar.
    3. Select
      OK
      .
    By default, the first extension uses
    1
    in the
    Extension number
    field. The number increases each time you add an extension to the current project, but you can change the number manually if necessary.
  5. If you selected
    Delete Entry
    , confirm the deletion if prompted.
    When an extension is deleted, the project's original due date is restored.
The project due date extension is added, updated, or removed. Added extensions appear in the
Extensions
column of the
Manage Projects
screen.