Project percent complete example

The
% Complete
field in the
Project
window shows the calculated percentage of budgeted hours for completed tasks compared to the total budgeted hours for the project.
In the
Project
window, the
% Complete
field is based on the budgeted hours for tasks that are marked as completed.
In the following example, two tasks are completed and one task is not started:
Project percent complete calculation example
Task
Budgeted Hours
Tracking
Task 1
5.0
Completed
Task 2
2.0
Completed
Task 3
3.0
Not Started
Project Total Budgeted Hours
10.0
NA
In this example, the calculation is:
% Complete
: (5.0 + 2.0) / 10.0 = 0.70, or 70%