DPS Batch Screening Monitor: Tracking Batch Processes
The
Batch Screening Monitor
screen provides visibility of batch processes to improve your view of process completion. This screen can be accessed by choosing Batch Screening Monitor from the DPS
menu.important
Updates in government regulation lists do not instantly trigger re-screening of Company Partners in DPS.
If a currently enabled denied list is updated (or a new one is added) after the last time a Company Partner was screened, that Company Partner will be screened against it per schedule in the system (proactive screening configured daily, weekly, etc.) or by a user action that dictates to do so (ad-hoc screening, Spreadsheet Upload, etc.).
When a Proactive screening (batch screening) is performed, the system initially selects all Company Partners found in Company Maintenance, except for those that have been manually blocked or with DTS Search Flag fields as 'No'. Then, it finally selects those that had been lastly screened prior to a denied list update (entity last screened date is lesser than Denied List change date).
To view batch processes.
- Click the calendar icon next toBegin Datefield and select the start date of the period you would like to view.

- Click the calendar icon next toEnd Datefield and select the end date of the period you would like to view.

- ClickSearch.

- The results within the period you selected will be displayed in theSearch Resulttab.
Search Result
In the
Search Result
grid you can see all data history according to the search criteria you provided. The batch processes are displayed according to the column’s descriptions below:Sarch criteria |
Meaning |
|---|---|
Batch ID |
The identifier number of the batch. |
Submitted Date |
The exact date and time the batch was triggered in the format: MM/DD/YYYY H:MM:SS AM/PM |
Total Records in BatchID |
The number of company partners records that are eligible to be screened by batch screening process. |
Submitted |
The number of company partners with submitted statuses. |
Finished |
The number of company partners with finished statuses. |
Failed |
The number of company partners with failed statuses. |
Elapsed Time |
The amount of time it has passed since this batch screening process was triggered. |
Estimated Remaining Processing Time |
If the batch status is In Progress, an estimated time on how much longer it will take to finish this batch screening process is displayed. It is an estimation; it may change due to batch load. |
Batch Status |
The status of the batch can be one of the following:
|
important
If a column has 'N/A' that means the column does not have applicable data to this batch process.
Batch Status
You can perform a search to filter the results for specific statuses.
- Click theBatch Statusdropdown and select the status you would like to view.

- ClickSearchand the results will be displayed.
Timeline Processing Scenarios
As part of risk analysis, Company Partner DPS status evolve over time. The system may clear it, block it after being screened or after finding matches, or others. Further screenings may keep the previous status or change it. Also, you may decide to override, deny or manually block a given Company Partner as needed.
The table below display possible scenarios you may encounter.
Day |
Events |
Results |
Status |
Comments |
|---|---|---|---|---|
0 |
You create or edit company partner. |
N/A |
Not screened |
N/A |
1 A |
|
1 match found |
Blocked |
N/A |
1 B |
You override company partner. |
N/A |
Overridden |
N/A |
2A |
|
1 match found |
Blocked |
Match found after override date. |
2 B |
You deny company partner. |
N/A |
Denied |
N/A |
3 |
Batch screens company partner. |
2 matches found |
Denied |
N/A |
4 |
|
1 match found |
Denied |
N/A |
5 A |
|
No match found |
Clear |
N/A |
5 B |
You manually block company partner. |
N/A |
Manual Block |
N/A |
6 |
N/A |
N/A |
Manual Block |
Manual block company partner(s) is excluded from proactive screening (A.K.A batch). |